Camille P. Balagtas
People's TONIGHT
August 22, 2002
Drilon warns against loan contract between Comelec and DBP
==========================================================
Senate President Franklin Drilon warned yesterday the Commission
on Elections (Comelec) and the Development Bank of the
Philippines against entering into any loan agreement that will
supposedly cover for the shortfall in the budget allocation of
the poll body for the year 2003.
"The Comelec is pre-empting the legislature in assuming that
Congress will indeed provide appropriations for the payments of
its loan," he said.
Drilon issued the warning in the wake of reports that Comelec is
trying to secure from the DBP a P5-billion loan, payable in ten
years, to finance the implementation of its various modernization
projects.
"Should both parties insist on the loan, the DBP would not
have any guarantee that it can be paid as proposed, 'Drilon said.
"Under the Constitution, no money shall be paid out of the
Treasury except in pursuance of an appropriation made by
law."
He added, "What if Congress refuses to appropriate funds in
payment of the loan? DBP will be left holding the bag.'
Drilon said at present, there is no indication that Congress will
enact the necessary appropriations.
"Congress cannot, at this point, give assurance to both the
Comelec and the DBP that it will include in the future General
Appropriations Acts the amount of money needed to pay the
loan," he said.
Drilon reminded the Comelec and the DBP of a similar transaction
in the past where the government and the Societe Generale
Surveillance (SGS) entered into a loan contract despite
objections from several lawmakers.
Eventually , the Congress refused to provide any appropriations
for the contract, which left both the government and the SGS in a
legal quandary. Up to this time, SGS cannot be paid for lack of
any appropriation from Congress.1///camille p. balagtas
Camille P. Balagtas
People's TONIGHT
August 22, 2002 SENATE HEARING
CE CASECNAN DEBUNKS ALLEGATIONS PROJECT IS ONEROUS AND
DISADVANTAGEOUS TO THE PHILIPPINES
=========================================================================================
CE Casecnan Water and Energy Company, Inc. (CE Casecnan) today
clearly demonstrated to the Senate that the Casecnan Project
contract is not onerous and disadvantageous to the Philippines as
has been alleged.
CE Casecnan president David Baldwin emphasized that the project
contract underwent extensive deliberations and negotiations, and
was duly authorized and approved by the Philippine government
through its relevant agencies. Negotiations were undertaken for
almost two years from 1993 to 1995.
Turning to the cost of Casecnan's electricity, Baldwin stated:
"Properly calculated, the output of the plant costs 1.8
pesos per kilowatt hour, among the cheapest sources of power in
the Philippines. Combined with the project's irrigation benefits,
the value of the Casecnan Project is clear."
The Casecnan project, which diverts water from two rivers through
a 26-kilometer tunnel to a generating plant, then on to the
Pantabangan Reservoir, was completed in 2001.
It will significantly contribute to enhancing the irrigation of
approximately 102,000 hectares and newly irrigating some 35,000
hectares of rice fields in Central Luzon. The project also has a
capacity of 150MW of electricity, and provides water to two
existing nearby hydroelectric plants, allowing these plants to
increase their output.
Achievement of commercial operation in 2001 began a 20-year
cooperation period outlined in the project agreement. At the end
of the 20-year period, CE Casecnan will turn over the project to
the government at no cost, after which it is expected to continue
commercial operation for an additional 30 years.
CE Casecnan Water and Energy Company, Inc. (CE Casecnan)
reiterated that the commencement of international arbitration to
require the National Irrigation Authority (NIA) to perform its
contractual obligations to reimburse certain taxes paid during
the construction of the Casecnan Multipurpose Irrigation Project
is unrelated to the Senate blue ribbon committee proceedings.
"We are not short-circuiting the Senate proceedings. CE
Casecnan participated in the hearings on August 8th and intends
to participate in the next hearing on August 22 as
requested," said David Baldwin, president of CE Casecnan.
Baldwin also clarified that "The Philippine government
approached CE Casecnan in March of 2001 to discuss the tax
reimbursement matter. We engaged in good faith negotiations which
culminated in a definite agreement with NIA in May of this
year."
"As request, we gave the government until the middle of July
to obtain the final approvals for the settlement, which it
unfortunately did not obtain. It was only then that we were left
with no choice but to seek resolution of the dispute on this
matter through arbitration, which is the method for resolving
disputes regarding the party's rights under the BOT Project
Agreement," he added.
Earlier, Administration Sen. Joker Arroyo, chairman of the Senate
Blue Ribbon committee, said the primacy of his committee in
conducting public hearings on the alleged lopsided Casecnan
multi-purpose project contract entered into by an American firm,
CalEnergy Casecnan Water and Energy Co. Inc. (CE Casecnan), with
the National Irrigation Administration (NIA) in 1995 cannot be
impaired by the filing of an arbitration suit by the American
firm with the International Chamber of Commerce (ICC).
Arroyo said the arbitration suit filed with the Paris-based ICC
very clearly seeks to "shortcircuit" the Senate Blue
Ribbon committee proceedings.
While the filing of the suit is lamentable, he said, the
committee will not be barred from resolving the issue as the
Senate has the power to investigate, in aid of legislation, or to
exercise its oversight functions.
"The committee hopes the CE Casecnan has not acted in bad
faith. The Blue Ribbon hearings are held in the performance of
legislative function and no outside proceedings can impair its
primacy or integrity on matters before it," Arroyo said.
The suit is focused on the contractor's demand for a
reimbursement on the $52 million it gave to the Philippine
government representing its advance tax payment.
Opposition Sen. Sergio Osmeņa had railed at an agreement entered
into between CE Casecnan and the NIA where the $52 million would
be $870 million in 20 years as computed at 48 percent interest,
compounded.
Osmeņa said the filing of the arbitration suit before the ICC
would have a negative implication on the part of the contractor.
"Too early. There is no finding (by the committee) yet nor
has the Executive Department revoked the contract,"
administration Sen. Ralph Recto, chairman of the Senate ways and
means committee, said.
Opposition Sen. Edgardo J. Angara, president of the Laban ng
Demokratikong Pilipino (LDP) party, said the suit is a
"pre-emptive action" to prevent the Philippine
government from investigating the firm which has resorted to
filing a lawsuit.
Angara said the American firm has to explain before the US
Securities and Exchange Commission (SEC) and the US Attorney
General's Office why it gave away 30 percent of its equity to two
firms as it gave the impression that it was bribery.
Osmeņa said he was surprised to hear the testimony of Oscar
Violago, president of San Lorenzo Ruiz Builders and a joint
venture partner of CE Casecnan, that he was given a 15 percent
equity share of the company because of his technical expertise
that led to the reduction of the cost of the $700 million
project.
The World Bank had estimated that the cost of the original
Casecnan trans-basin project was $2 billion.
He said he was also surprised to learn that CE Casecnan also gave
out another 15 percent equity share to Laprairie, a heavy
equipment firm based in Canada's British Columbia.
Another opposition legislator, Sen. John H. Osmeņa, said the
filing of the arbitration suit is expected as the negotiation for
the onerous provisions of the contract would get more touchy and
tougher.
Osmeņa said the filing of the suit will not stop the Senate
probe and it will get "more interesting and detailed"
in the days to come, he said.
"It is a counter-attack. Offense is the best defense,"
Osmeņa remarked.
He cited reports that Violago is a close personal friend of the
family of former President Ramos.
The Senate wants to investigate most of the 42 controversial
Independent Power Producer (IPP) contracts signed by Ramos during
his term although he had been warned by the World Bank not to
sign more IPP contracts as the electric power to be produced by
the originally small number of IPP contracts already met the
country's power requirement.
The Osmeņa cousins had charged that the total IPP contracts
signed by Ramos have power ratings twice the power requirement of
the country which was more than 6,000 megawatts.
Opposition Sen. Aquilino Q. Pimentel Jr. said the American firm
should not have filed the arbitration suit "because it sets
a very bad precedent."
He said the suit has the effect of trying to stopping the Senate
in inquiry into issues raised before the committee.
Senate President Franklin M. Drilon said the Senate will continue
its investigation and expose any irregularities.
"We will not be stampeded into approving contracts," he
added.///camille p. balagtas